How solar panels are installed on a roof
From the first roof survey to PG&E's permission to operate. Every step, what happens on your roof, and how long it usually takes.
- The work on your roof usually takes one to three days. The full project, from contract to switching on, typically runs two to three months because of design, permits, inspection and PG&E approval.
- Panels mount on aluminum rails bolted into the rafters through flashed attachments that shed water like a shingle.
- If your roof has less than 10 years of life left, plan the re-roof first.
A rooftop solar install looks quick from the street: a crew arrives, and a day or two later the panels are up. Behind that are a site survey, an engineered design, a city permit and a utility approval. Knowing the sequence helps you spot a careful installer and plan around the steps that take the longest.
Is your roof ready for solar?
- Age and condition. Panels last 25 years or more. If the roof will need replacing within about 10 years, re-roof first. Removing and reinstalling an array later costs real money.
- Structure. A typical array adds a few pounds per square foot. Most roofs carry it easily, but older framing, especially in pre-war homes, gets checked by an engineer.
- Orientation and shade. South, west and east faces all work. Heavy shade from trees or neighboring buildings is the bigger concern.
- Space and setbacks. California fire code requires clear pathways on the roof for firefighters, which reduces usable area, especially on small or steep roofs.
The install, step by step
- Site survey. A technician measures the roof, photographs the attic framing, checks the electrical panel and records shade.
- Design and engineering. Panel layout, rail spans, attachment spacing and electrical plans are drawn, with structural calculations where needed.
- Permit. Plans go to your city's building department. Many Bay Area cities offer streamlined online solar permitting.
- Attachments and flashing. On install day, the crew locates rafters and installs mounts, each sealed with flashing that tucks under the roofing above it.
- Rails and panels. Aluminum rails bolt to the mounts. Panels clamp to the rails and are grounded together.
- Electrical. Wiring runs in conduit to the inverter, battery and main panel. Rapid shutdown equipment lets firefighters de-energize the roof.
- Inspection. A city inspector checks the structural and electrical work against the approved plans.
- Permission to operate. PG&E reviews the interconnection and gives written approval. Only then is the system switched on.
Don't switch it on early. Running the system before PG&E's permission to operate breaks the interconnection rules. Your installer should tell you when approval arrives.
How leaks are prevented
Every bolt through the roof is a potential leak, so the attachment method matters more than the panel brand. On composition shingle roofs, each mount sits under a metal flashing that slides beneath the shingle course above, so water flows over it rather than into it, with sealant as a second layer. Tile roofs use tile hooks or replacement flashed tiles. Flat roofs, common in the Sunset and Richmond districts, often use ballasted or low-profile attachments with roofing-compatible flashing.
A good installer offers a written workmanship warranty that covers roof penetrations for at least 10 years.
Typical timeline
| Stage | Typical duration |
|---|---|
| Survey and design | 1 to 3 weeks |
| City permit | Same day to several weeks, by city |
| Installation on site | 1 to 3 days |
| City inspection | Usually within 1 to 2 weeks of install |
| PG&E permission to operate | Often 1 to 4 weeks after inspection |
Start with a real roof survey.
We check roof age, framing, shade and your panel before we quote.
Questions to ask any installer
- Who does the install: your own crew or a subcontractor?
- What attachment and flashing method will you use on my roof type?
- How long is the workmanship warranty, and does it cover roof leaks?
- Does my main panel need work, and is that in the price?
- Who handles the permit, inspection and PG&E interconnection?